Introduction
Placing concrete under water is a specialized subject and should be avoided whenever practical to do so. Where concrete works have to be constructed below water level as in the case of marine works, deep foundations of bridges etc; one of the two courses may be adopted. Either water may be excluded temporarily from the site by using cofferdams, caissons, pumps, dewatering equipment OR Concrete may be placed in water using special methods.
Whilst concrete will set and harden under water its placing presents several problems. The most difficult is the prevention of segregation and loss of cement. Formwork except for simpler forms of construction, is difficult to place accurately and in all cases must be anchored firmly. In view of these difficulties, underwater concreting in generally confined to mass un-reinforced work and consideration should always be given to use of pre-cast block for the whole work or as permanent formwork.
General Requirements
- Concrete should not be placed underwater when the temperature of water is below 4°C.
- It requires a very workable concrete with slump as high as 7" and cement content upto 650 Ibs/cuyd.
- Placing is done in caissons, confer dam or forms.
- Foundation clean up is required using hydraulic jets or pumps.
- Concrete must not be placed in running water.
- Concrete must not be allowed to fall in water.
- Concrete should not flow horizontally by more than 10 ft.
Equipment and Techniques of Concreting Under Water
Under Water Bucket
Concrete Pouring with Buckets |
Concrete for the purpose will have 6-7 sacks of cement per cuyd, 6“ - 7" slump, 1.5“ _ 2" maximum size of aggregate and sand content higher than normal; 40% or more. Concrete for foundation of Franciso Bay Bridge was placed in water as deep as 240 ft with buckets. Bucket placement is a good way to start a placement by the tremie method. The later is probably faster and possibly superior once started. Tremie is operated when concrete layer 2 to 3 ft thick is placed.
Tremie
It consist of placing concrete through a vertical pipe, allowing the concrete to flow from the bottom. The bottom of the tremie is kept submerged in the concrete all the times, and the concrete flows into the mass of previously placed concrete.A tremie consist of a pipe usually 10"-12" inch diameter with a hopper or funnel at the upper end. The equipment is adequately supported and arranged so that it can be raised and lengths of pipe can be removed if necessary as the level of concrete rises in the form. The spacing of the tremie should not be more than 12 ft to 16 ft apart or 8' from the sides or ends of enclosure.
Concrete is delivered to the hopper by bucket, truck mixer, pump or conveyor. The delivery must be at a good rate and without interruption. Delay for any reason impairs the free flowing mobility of the mass into which concrete is being placed. Plugged pipe and cold joints can result from delays.There are two basic methods of starting a tremie, which may be called the " wet pipe" and "dry pipe" method.
Tremie |
Pumps
Concrete Pump |
Pre placed aggregate concrete
- Economical in cement content. 200 - 250 Ibs /cuyd of cement is used as against 600-800 Ibs/cuyd. Normal strength is 2900 psi.
- Uniform properties through out the mass.
- High durability
- Low permeability
- Suitable for placing in congested areas and where instruments are to be located precisely.
- Suitable for under water concreting.
- Reduced shrinkage due to point contact of aggregate particles. Drying shrinkage 200 x 10-6
- No cracking because of low shrinkage.
- Aggregate, while in place can be cooled or heated.
- Suitable for mass construction.
- Suitable for repair of old structures.